Today it was time to start with the walls. We are using "Superblock" - Aerated concrete blocks, 60x20cm. They are not so heavy and very easy to work with. The mortar is like a mix between concrete and glue. We have asked the tree company to deliver frames for doors and windows so the walls will not be complete yet.
One of the first things that the team set up on the land was the small BIO (Building Inspector office). Now its time to dig here for the waste-water pipes and also the place where the parking should be set up. So the move was done this morning.