Completing the floor beams on first floor

For some days now, the work have been focused to get the floor beams on first floor done.
I have here a lot of pictures from the framework to the ready beams.

Setting up the metal forms

Forms in place

Measures the bathroom floor

A lot of tree is needed to stable the forms



The concrete truck cannot get the concrete up to the forms, so there is a lot of manual lifting.




Forms removed

Special chemicals used to keep the concrete moist for the first important days.



Comments

Popular posts from this blog

Pictures from downstairs

Some pictures from today.

Community water

Perfect timing. The community have started to dig and mount water pipes right outside my fence, so I will get water from both the well and the community = no future water problems!

Many bars

Back to work, Today the workers done many rebar "cages" after delivery of materials and a rebar machine. The three cages that was done before was made of 16 mm rebar that was a leftover from their last work. Now the rebar is 12 mm (as planned). Some pictures: