Today the termite group arrived. They need to install pipes on the beams where chemicals will be transported and dripping out to prevent termites under the house.
It's a bit scary with this chemicals, but this is how they do it when building houses and they tell it will not smell or cause any troubles.
The installation and three years of maintenance was included in the contract with the builder. After that the termite team will come and fill more in the pipes when I call them.

After installation they sprayed some chemicals on the soil between the beams.








Comments

Popular posts from this blog

Pictures from downstairs

Some pictures from today.

Arrival of the roof tiles

The roof tiles arrived today at 06.00 in the morning. No pallet, it looked like they have unloaded the truck manually. They delivered over 4000 tiles! One of the three piles of tiles delivered. Some broken due to the bad handling. Lintels in aluminum to hold the roof tiles. More lintels

Parking

The builders have started with the pillars of the parking. This is just the start of the parking project. It's important to fence-in a building project to keep non-authorized people out. Foreman is checking Forms in place Pouring cement into the forms The foreman with his laser