Waiting for material

Not enough rebars (steel reinforcement bars)!
The delivery of materials have been scheduled to Tuesday, so no progress on the form preparation today. The workers spend time to set up an office for us, where we can have meetings, drink and eat when we visit the site.
A big poster is set up with pictures of all the steps needed to be done for the current building phase. Right now it's pictures describing how to do the foundation in the right way.


The office. The poster is on the right side.
The extra roof at the front was added after test in the bright sunshine.

Poster. Observe all this bubbles with descriptions on the pictures - Important.
Some pictures are missing, have to buy more glue.

Comments

Popular posts from this blog

Pictures from downstairs

Some pictures from today.

Arrival of the roof tiles

The roof tiles arrived today at 06.00 in the morning. No pallet, it looked like they have unloaded the truck manually. They delivered over 4000 tiles! One of the three piles of tiles delivered. Some broken due to the bad handling. Lintels in aluminum to hold the roof tiles. More lintels

Parking

The builders have started with the pillars of the parking. This is just the start of the parking project. It's important to fence-in a building project to keep non-authorized people out. Foreman is checking Forms in place Pouring cement into the forms The foreman with his laser