First level of beams

Full speed working with the forms to the first level of beams.
There are now 12 people working on the site. When the concrete work is done, some of them will move to next project and be replaced with workers with other skills.




Comments

Popular posts from this blog

Pictures from downstairs

Some pictures from today.

Community water

Perfect timing. The community have started to dig and mount water pipes right outside my fence, so I will get water from both the well and the community = no future water problems!

Many bars

Back to work, Today the workers done many rebar "cages" after delivery of materials and a rebar machine. The three cages that was done before was made of 16 mm rebar that was a leftover from their last work. Now the rebar is 12 mm (as planned). Some pictures: