First Concrete

Today it was time to add concrete to the platforms that was ready for it.

Was everything ready for concrete?
Rebar - check
Pillar rebar connection - check
Cleaned - check
Distances in place - check
Forms ok - check
Concrete quality - check
Vibrators connected and working - check

OK, two concrete trucks arrived - 4 m3 was poured into the forms

To avoid to much moving of the soil, only half of the holes/platforms are ready for concrete. Later on when these are ready, they start with the remaining ones. The vertical rebars is for the pillars from the platform and up to the ground.


Important to keep the area clean.

Concrete Truck

Ready to start filling the forms

Filling, many workers.


Using vibrators to get air out from the concrete.

Looks good?




Noticed something on this photo.
Check the nice repair of the electrical socket/wires. 
Not so important here - enough secure to get the job done.


Comments

Popular posts from this blog

Pictures from downstairs

Some pictures from today.

Arrival of the roof tiles

The roof tiles arrived today at 06.00 in the morning. No pallet, it looked like they have unloaded the truck manually. They delivered over 4000 tiles! One of the three piles of tiles delivered. Some broken due to the bad handling. Lintels in aluminum to hold the roof tiles. More lintels

Parking

The builders have started with the pillars of the parking. This is just the start of the parking project. It's important to fence-in a building project to keep non-authorized people out. Foreman is checking Forms in place Pouring cement into the forms The foreman with his laser