Building start - Breaking ground

Time to start.
The house ceremony is planned for first of November, but that doesn't stop the newly arrived workers to start digging. The soild was to hard to dig by hand, so the builder ordered in a digger. Here is a collection of pictures from the first digging day.
Checking heights - very important

Digging, the holes will be 1.5 meter deep.

Inspecting

There will be high piles of soil on the land

Digger, Japanese quality.

Packing sand at the bottom of hole.

Frames for the first layer of concrete. 
In Sweden we use polystyrene sheets instead.

Concrete work.

More inspections

Checking height.

There will be many holes. 25 platforms will be used to hold up the house.
Some holes will have more than one platform.

OK, first layer done in this hole.


Quite a lot was done after just one days work.

Comments

Popular posts from this blog

Pictures from downstairs

Some pictures from today.

Community water

Perfect timing. The community have started to dig and mount water pipes right outside my fence, so I will get water from both the well and the community = no future water problems!

Many bars

Back to work, Today the workers done many rebar "cages" after delivery of materials and a rebar machine. The three cages that was done before was made of 16 mm rebar that was a leftover from their last work. Now the rebar is 12 mm (as planned). Some pictures: